10/05/2004

We got a trash pen in front of our foundation today!

 

10/12/2004

The flooring system is delivered

 

 

 

 

days 'til our estimated closing date.

 

 

       Wally and Chris' New Home Adventure

July 18 - July 24           July 29 - August 2              August 25 - Sept 2      

Build It Now              Sept 9              September 10       

Huge Events Today on Lot 10     September 16            September 22

James Dean Day 092504    Alien Abductions         Foundation Day 092904

October 1 2004         Cookout_Day    Punk Gone Wrong     Northfield Sign Installed

October 4 2004    October13 2004   Framing Day   secondfloor and trusses delivered  

2nd floor framed     roof installed   October 22 2004   October 25 2004

Windows and Doors  Trim installed    Garage Door    electrical and plumbing   

 Shingles installed       Siding Installed  drywall installed      bricks        Brick Laid    

 Interior Doors and Trim Delivered   Fireplace Mantle and Marble Installed        More Plumbing       

We Have Carpet Now          Quality Check    

Move In Day December 22, 2004

 

       Wally and Chris' New Home Adventure

July 18 - July 24           July 29 - August 2              August 25 - Sept 2      

Build It Now              Sept 9              September 10       

Huge Events Today on Lot 10     September 16            September 22

James Dean Day 092504    Alien Abductions         Foundation Day 092904

October 1 2004         Cookout_Day    Punk Gone Wrong     Northfield Sign Installed

October 4 2004    October13 2004   Framing Day   secondfloor and trusses delivered  

2nd floor framed     roof installed   October 22 2004   October 25 2004

Windows and Doors  Trim installed    Garage Door    electrical and plumbing   

 Shingles installed       Siding Installed  drywall installed      bricks        Brick Laid    

 Interior Doors and Trim Delivered   Fireplace Mantle and Marble Installed        More Plumbing       

We Have Carpet Now          Quality Check    

Move In Day December 22, 2004